2016 Storm Sewer Improvements-Notice to ProceedSECTION 00 55 00 - NOTICE TO PROCEED
Dated 3131 I I LP
TO: Thompson Construction, Inc.
(CONTRACTOR)
ADDRESS: 2404 N. Lincoln Ave.
Fremont NE 68025
Project: 2016 Storm Sewer Improvements — Various Sites, Blair, Nebraska
You are notified that the Contract Times under the above contract will commence to run on
July 1, 2016. By that date, you are to start performing your obligations under the Contract
Documents. In accordance with Article 4 of the Agreement the project shall be completed and
ready for final payment within sixty (60) calendar days and no later than October 1, 2016.
Before you may start any Work at the Site, you must
(add other requirements)
City of Blair
(OWNER)
0
ORIZED SIGNATURE)
James Realph, Mayor
(TITLE)
Acknowledgement of Receipt
CONTRACTOR
21
Name Title
Date