2016 Storm Sewer Improvements-Notice to ProceedSECTION 00 55 00 - NOTICE TO PROCEED Dated 3131 I I LP TO: Thompson Construction, Inc. (CONTRACTOR) ADDRESS: 2404 N. Lincoln Ave. Fremont NE 68025 Project: 2016 Storm Sewer Improvements — Various Sites, Blair, Nebraska You are notified that the Contract Times under the above contract will commence to run on July 1, 2016. By that date, you are to start performing your obligations under the Contract Documents. In accordance with Article 4 of the Agreement the project shall be completed and ready for final payment within sixty (60) calendar days and no later than October 1, 2016. Before you may start any Work at the Site, you must (add other requirements) City of Blair (OWNER) 0 ORIZED SIGNATURE) James Realph, Mayor (TITLE) Acknowledgement of Receipt CONTRACTOR 21 Name Title Date 00 55 00-1 Issuance 2/1/05 Revised 4/10