Checkoff Sheet MS-2014-02820.tif i
i
I NTERNATIONAL `
CITY OF BLAIR REROOFING CHECKOFF SHEET
I
R to B lair City Hall prior to Final Inspection
21 1 Street, B lair, NE 68008
Because of limitations caused by the infeasibility to perform detailed inspections which would
not interfere with reroofing work, please indicate compliance with the following requirements
fallowing this reroofing job.
i
Property Address: 3030 Westridge Drive
Contractor or Homeowner (if self) Quality Home Exteriors LLC
Permit #: MS-2014-
Installation Date; 11 /5/14
YES NO
Q ✓ The materials and methods of application used for recovering or replacing the existing j
roof covering comply with the requirements of the building cede. (8907.1)
ICE PROTECTION INSTALLED An ice barrier that consists of at bast two layers of
underlayment or of a self-adhering polymer modified bitumen sheet was installed and �
extends at least from the eave's edge to a point at least 24 inches inside the exterior j
wall line of the building. (R906.2.7.1)
❑✓ STRUCTURAL COMPONENTS ARE SOUND: The structural roof components are
capable of supporting the roof covering system and the material and equipment loads
that will be encountered during installation of the roof covering system. (R907.2)
i
✓� 13 EXISTING COVERING WAS REMOVED: Existing roof covering was removed for one
of the reasons required by section 890753
�✓ 0 DID NOT USE RUSTED METAL OR FLASHING,. Existing vent flashing, metal edges,
drain outlets, collars or metal counter - flashing were not reinstalled if rusted. (R907.5)
❑✓ 0 FLASHING INSTALLED PROPERLY: Flashing shall be reconstructed in accordance
with approved manufacturer's installation instructions. Metal flashing to which
bituminous materials are to be adhered shall be primed prior to installation. (R907.6)
12/4/14
Signature of Primary Installer Date
34Z;2.'z1 Z�)4�Izd 12/4/14
Signature of Permit Holder Date