Checkoff Sheet MS-2014-00488_0001.tif i
2009 INTERNATIONAL RESI E I
CITY OF BLAIR REROOFING CHECKOFF SHEET
Return to Blair City Hall prior to Final Inspection
218 S 16 i Street, Blair, NE 68008
Because of limitations caused by the infeasibility to perform detailed inspections which would
not interfere with reroofing work, please indicate compliance with the following requirements j
following this reroofing job. j
Property Address: '
Contractor or Homeowner (if self)
Permit #: MS- 2014 -
Installation Date: 1 1 ZY
YES NO
❑ The materials and methods of application used for recovering or replacing the existing
roof covering comply with the requirements of the building code. (R907.1)
❑ ICE PROTECTION INSTALLED An ice barrier that consists of at least two layers of
underlayment or of a self - adhering polymer modified bitumen sheet was installed and
extends at least from the eave's edge to a point at least 24 inches inside the exterior
wall line of the building. (R905.2.7.1)
STRUCTURAL COMPONENTS ARE SOUND: The structural roof components are
capable of supporting the roof covering system and the material and equipment loads
that will be encountered during installation of the roof covering system. (R907.2)
❑ EXISTING COVERING WAS REMOVED: Existing roof covering was removed for one
of the reasons required by section R907.3 �
❑ DID NOT USE RUSTED METAL OR FL ASHING: Existing vent flashing, metal edges,
drain outlets, collars or metal counter- flashing were not reinstalled if rusted. (R907.5)
❑ FLASHING INSTALLED PROPERLY: Flashing shall be reconstructed in accordance
with approved manufacturer's installation instructions. Metal flashing to which
bitumin us materials are to be adhered shall be primed prior to installation. (R907.6)
Signature o Pr a 1 �staller
g t at e
Signature of Permit Holder Date