Checkoff Sheet MS-2014-01565_0001.tif i
i
2009 INTERNATIONAL RESIDENTIAL CODE
CITY OF BLAIR REROOFING CHECKOFF SHEET
Return to Blair C Hall prior to Final Inspection
218 S 16 Street, Blair, NE 68008
Because of limitations caused by the infeasibility to perform detailed inspections which would
not interfere with reroofing work, please indicate compliance with the following requirements j
following this reroofing job.
Property Address:
Contractor or Homeowner (if self)
Permit #: MS -2014-
Installation Date:
x
YES NO
❑ The materials and methods of application used for recovering or replacing the existing
roof covering comply with the requirements of the building code. (R907.1)
❑ ICE PROTECTION INSTALLED An ice barrier that consists of at least two layers of '
underlayment or of a self- adhering polymer modified bitumen sheet was installed and
extends at least from the eave's edge to a point at least 24 inches inside the exterior
wall line of the building. (R905.2.7.1)
❑ STRUCTURAL COMPONENTS ARE SOUND: The structural* roof components are
i
capable of supporting the roof covering system and the material and equipment loads
that will be encountered during installation of the roof covering system. (R907.2)
❑ EXISTING COVERING WAS REMOVED: Existing roof covering was removed for one
of the reasons required by section R907.3
❑ DID NOT USE RUSTED METAL OR FLASHING: Existing vent flashing, metal edges,
drain outlets, collars or metal counter - flashing were not reinstalled if rusted. (R907.5)
❑ FLASHING INSTALLED PROPERLY: Flashing shall be reconstructed in accordance
with approved manufacturer's installation instructions. Metal flashing to which
bituminous materials are to be adhered shall be primed prior to installation. (R907.6) 9 - /,V
.
i
Signature of Prima Instal r Date
/
Signature of Per it older Date
i