ac-76_0006.jpg 5) Frame Inspection: To be made after the roof, all framing, fire blocking and bracing are
in place and all pipes, chimneys and vents are complete and the rough electrical,
plumbing, and heating wires, pipes, and ducts are approved.
Note: Framing inspections are required upon completion of the rough -ins for electrical,
plumbing, and mechanical, This includes the completion of fire stopping, draft stops, and
bracing.
Note: Drywall inspections for fire- resistance rated construction shall be inspected prior to any
plaster being installed or wallboard joints being taped and finished.
6) Permanent Service: The City of Blair requires a building or structure to be fully
enclosed prior to accepting a permanent service (siding need not be complete, as long as
the structure is tight from the weather elements.) Once the service has been approved,
the City will fax the approved inspection to OPPD.
The permanent service shall have a GFCI receptacle on each floor including the
basement. This requirement shall be completed prior to approving an inspection for
permanent service. Note: Generally this inspection should be requested on or prior to
your drywall inspection.
Note: All meter service equipment shall be installed in or directly attached on single family
dfvellings.
7) Final Inspection: To be made after the building is completed and ready for occupancy.
There shall be a final inspection and approval of all buildings and structures when
completed and ready for occupancy and use.
Note: Failure to comply with a final inspection acrd /or allow occupancy prior to a final
inspection will result in FORFEITURE of the deposit.
8) Septic Systems: Septic Tank and laterals shall be inspected for proper installation and to
ensure their size of tank and laterals will work for that property.
9) Stop Box Location Cards: These cards must be completed and returned to City Hall
before the building deposit can be refunded.
10) All Commercial /Industrial construction requires review and approval of the State Fire
Marshal's Office. This review is your responsibility. Forms can be obtained at City Hall.
NOTE: ALL SINGLE FAMILY DWELLINGS CONSTRUCTED WITHIN THE
CORPORATE LIMITS OF THE CITY OF BLAIR OR WITHIN THE ZONING
JURISDICTION LIMITS OF THE MUNICIPALITY SHALL HAVE ROOF EAVES OF
NOT LESS THAN TWELVE INCHES (12 ").