ad-2011-00142_0009.jpg 1.0.1.9 Temporary support of the existing stair stringers, after removal of
the concrete landing in order to maintain access to the existing loadout
platform during this construction period.
1.0.1.10 Relocation and anchorage of the existing emergency shower.
1.0.1.11 Supply and install PVC piping drainage system to curbed area
for relocated emergency shower as noted on the plans.
1.0.1.12 Caulking around all piers, slab and joints noted on the
construction drawings. Note: water stops are not necessary; caulking will
be sufficient
1.0.1.13 Supply, fabrication and installation of hand railing at the new
doorway. New door will be by others.
1.0.1.14 Supply and installation of the 4" stainless steel drain pipe with
stainless steel screening at each end through new concrete curbing under
the existing loadout platform.
1.0.2 All work to be scheduled and performed between loadout operations.
Construction activities shall take place starting on Wednesdays at 2:00
p.m. and finishing on Monday mornings at 6:00 a.m. (Monday at 6:00
a.m. to Wednesday at 2:00 p.m. to be considered loadout operations.)
During loadout operations, all construction operations must STOP and
the contractor shall maintain temporary containment dikes or curbs
around any open construction within the existing dike area prior to and
during the loadout operations.
1.0.3 If working at night; contractor to provide own construction lighting if
needed.
1.0.3.1 Natureworks LLC will provide electrical connections for
temporary lighting if needed.
1.1 Work By Others
Work not included in this package includes:
1.1.1 Grounding
1.1.2 Piping, other than noted in section 1.0.
1.1.3 Electrical
1.1.4 Instrumentation
1.1.5 Steel Enclosure
1.1.6 Insulation
1.1.7 Heat tracing
1.1.8 Roofing
1.1.9 Siding
1.1.10 Grouting of column anchor bolts.
2of3