=cn-2010-00284_0001.tif Howard Wolfe
From: Howard Wolfe
Sent: Monday, December 27, 2010 9:41 AM
To: 'gary@comaciconstruction.com'
Cc: Howard Wolfe
Subject: Control Substation 1341 - Cargill -12 -27 -2010
Date: 12 -27 -2010
Re: Cargill Control Substation 1341 building
Gary: Please respond to the following plan review comments:
1. Provide stamped engineered structural drawings that indicate the size and material for the structural frame of the
building.
2. Provide a mechanical permit application and mechanical plans.
3. Is there any plumbing work?
3. List required Special Inspections on the plans. Who is doing the Special Inspections?
4. Soil bearing is assumed by the engineer as 2000 psf. Provide a copy of the soils investigation report.
5. Provide Energy Calculations as per State requirements.
6. Note: Provide plans to State Fire Marshals Office as well.
7. Provide Engineers Phone number, Company name, and E -mail address.
Thank -you,
Howard Wolfe
Building Inspector
City of Blair
218 South 16th Street
Blair, NE 68008
Office: (402) 426 -4191
Direct: (402) 426 -6696
Fax: (402) 426 -4195
hwolfe @ci.blair.ne.us