2010-08RESOLUTION
WHEREAS, there has been signed by the City of Blair on the
28th day of March , 2006 , and the State on the 6th day of
April , 2006 , an agreement providing for the construction of a Federal
Aid Project at the following location: connecting the Blair Deerfield Lions Trail to the Dana College
softball and recreational fields.
WHEREAS, in the above agreement, the City has pledged sufficient funds to finance its share of
the cost of the construction of this project identified as STPB- 89(24) , and
WHEREAS, the above mentioned agreement provided that the City would pay costs as set forth
in the agreement, and
WHEREAS, the State and the City received bids for the construction of this project on
January 28, 2010 , at which time six bids were received for the construction of the
proposed work, and
WHEREAS, the following contractor(s) has been selected as the low bidder to whom the
contract(s) should be awarded:
Tab Holding Company, Inc., DBA Tab Construction, Omaha, Nebraska
Concrete Pavement: $356,786.42
NOW THEREFORE, in consideration of the above facts, the City Council of the City of
Blair , by this resolution, takes the following official action:
1. The Council hereby concurs in the selection of the above mentioned contractor(s) to whom the
contract(s) should be awarded.
2. The Council does not desire to perform any of the work with its own forces in lieu of performing
the work by the contract method.
3. The Council hereby authorizes the Mayor and the City Clerk of Blair
to sign the construction contract on behalf of said City.
DATED THIS 9th DAY OF February
CON1 -PN
CITY OF
Mayor
Council Member Abbott
Moved the adoption of said resolution.
Roll Call:
, and
, A.D. 2010
BLAIR
8 yea, 0 nay.
Resolution adopted, signed and billed as adopted.
STATE OF NEBRASKA )
) ss:
WASHINGTON COUNTY )
BRENDA R. WHEELER, hereby certifies that she is the duly appointed, qualified and acting
City Clerk of the City of Blair, Nebraska, and that the above and foregoing Resolution was
passed and adopted at a regular meeting of the Mayor and City Council of said City, held on the
9th day of February, 2010.
BRENDA R. WHEELER, CITY CLERK
ORIGINAL
CALL ORDER : 250 CONTRACT ID : 2220X COUNTIES : WASHINGTON
LETTING DATE : 01/28/10 DISTRICT : 2
CONTRACT DESCRIPTION : PROJECT(S) : STPB- 89(24)
BLAIR -DANA TRAIL, BLAIR
VENDOR NO. BID NOTES
TOTAL % OVER
RANK VENDOR NO. /NAME BID LOW BID
1 2364 TAB HOLDING COMPANY, INC., DBA TAB CONSTRUCTION $ 356,786.42 100.0000%
2 0385 MFT CONSTRUCTION, INC. $ 393,888.80 110.3990%
3 3709 NAVARRO ENTERPRISE CONSTRUCTION, INC. $ 401,178.03 112.4421%
4 1613 M. E. COLLINS CONTRACTING COMPANY, INC. $ 419,876.52 117.6829%
5 0103 CHAS. VRANA & SON CONSTRUCTION CO. $ 423,931.86 118.8195%
6 1416 LUXA CONSTRUCTION COMPANY, INCORPORATED $ 441,619.15 123.7769%
NEBRASKA DEPARTMENT OF ROADS DATE : 01/28/10
PAGE : 2
VENDOR RANKING