2020 Olsson Agreement BTA SA-08 Pave Taxilane-1st Amendmentr "I- AMENDMENT NO. 1 to AGREEMENT FOR CONSULTING SERVICES BLAIR AIRPORT AUTHORITY 218 South 161h Street Blair, NE 68008 Re: AMENDMENT TO CONSULTANT AGREEMENT BLAIR MUNICIPAL AIRPORT BTA SA -08 Olsson Project No. 019-3437 This amendment will revise the Agreement executed on November 11, 2019 by adding Section 5A and 5B and amending Section 7, as described below: SECTION 5A: CONSTRUCTION SURVEY PHASE SERVICES a. Provide site control points for construction commencement. SECTION 513: CONSTRUCTION OBSERVATION PHASE SERVICES based on 15 working days (construction contract time) a. Provide consultation and advice to the Sponsor during construction phase. b. Assign a Project Engineer to the project who will periodically observe work in progress. c. Participate in preconstruction conference and submit meeting minutes. d. Upon receipt of NDOT authorization, the Consultant will issue, for the Sponsor, the Notice to Proceed to the Contractor. e. Review and approve shop and erection drawings and all materials data submitted by construction contractors for compliance with design concepts. f. Provide part time on-site construction observation. Estimated site visits: 8 partial day observation. g. Prepare and negotiate contract modifications, change orders and supplemental agree- ments. h. Contract requires Contractor to complete all testing for the project. Consultant will coordinate with Contractor to ensure that all testing requirements have been met. Contractor is responsible for submitting test results in a timely manner to allow for Consultant to review the results. i. Determine amounts owed to construction contractors and process financial documents. j. Arrange and conduct final inspections. Submit a summary of test results complete with acceptance test results and pay factor adjustments. k. Prepare as -built record drawings. SECTION 7: FEES AND CHARGES — Additional Items The Sponsor shall pay the Consultant for the services described in this amendment as follows: Section 5A: Construction Survey Phase. Payment for the items included in Section 5A, Construction Survey Phase, shall be the lump sum of $2,800 shown on Exhibit E, attached and made a part hereto. Payment shall be due monthly based on the percentage of work completed. Section 513: Construction Observation Phase. Payment for the items included in Section 513, Construction Observation Phase shall be made based on direct salary, overhead costs and reimbursable expenses incurred plus a fixed payment and subcontract costs. The schedule of charges and reimbursable expenses is Exhibit F attached and made a part hereto. Labor and general administration overhead percentage shall be supported by a statement of overhead expenses certified by the consultant's auditor or a governmental auditor. The total charges for Section 5134 will not be greater than the "Not -to -Exceed" (NTE) amount of $16,900, if 1) the construction work is completed within the construction contract aggregate time allowance; and 2) the scope of work as set forth in Section 1 is not exceeded. If either of these two events occur, the "Not -to -Exceed" amount may be increased by a supplemental agreement to this contract. No payment above the Not -to -Exceed limit shall be made without prior approval of an amendment supported by proper justification. Payment shall be due monthly for incurred charges and expenses based on detailed invoices. Invoices shall include a pro rata portion of the fixed fee with the final invoice adjusted to include the remaining unpaid balance of the fixed fee. If this amendment is satisfactory, please sign in the space provided. Keep one copy and return one copy to Olsson. This proposed amendment is open for acceptance for thirty days from the date set forth above, unless changed by us in writing. OLSSO By BLAIR AIRPORT AUTHORITY `1r , (Al Attest Date �'' "0O.C) v By I,,a14_ mat x' i4pvyl 1�.�.+-o!'t- EXHIBIT E CONSTRUCTION SURVEY PHASE Blair Municipal Airport BTA SA 08 1. Direct Salary Costs Rounded: $2,800.00 " For Item 2, the consultant should submit a statement of auditable overhead expenses, certified by the consultant's auditor, the sponsor's auditor, the state's auditor, or a Federal government auditor. Direct Salary Total Title Hours Rate/Hour Costs Team Leader 0.0 $80.24 $0.00 Sr. Project Engineer 2.0 $64.06 $128.13 Project Engineer 0.0 $56.42 $0.00 Elec. or Mech. Engineer 0.0 $73.94 $0.00 Assistant Engineer 0.0 $39.10 $0.00 Registered Surveyor 4.0 $51.95 $207.79 Sr. Technician 8.0 $31.56 $252.51 Assoc. Technician 8.0 $30.37 $242.94 Asst. Technician 0.0 $28.08 $0.00 Sr. Clerical 0.0 $29.90 $0.00 Total Direct Salary Costs: $831.38 2. Labor and General & Administrative Overhead Percentage of Direct Salary Costs* 184.12% $1,530.73 3. Fixed Fee: 15% of Item 1 & 2 $354.32 4. Direct Nonsalary Expenses Travel $100.00 Meals & Motel $0.00 Copies & Prints $20.00 Supplies, Phone, Misc. $0.00 Total Expenses: $120.00 5. Subtotal of Items 1 - 4 $2,836.42 6. Subcontract costs $0.00 7. Lump Sum Amount - Total Items 5 & 6 $2,836.42 Rounded: $2,800.00 " For Item 2, the consultant should submit a statement of auditable overhead expenses, certified by the consultant's auditor, the sponsor's auditor, the state's auditor, or a Federal government auditor. EXHIBIT F CONSTRUCTION PHASE SERVICES Blair Municipal Airport BTA SA 08 Based on estimated 15 working days 1. Direct Salary Costs Direct Salary Hours Rate/Hour Title Team Leader Sr. Project Engineer Project Engineer Elec. or Mech. Engineer Assistant Engineer Registered Surveyor Sr. Technician Assoc. Technician Asst. Technician Sr. Clerical 0.0 $80.24 21.0 $64.06 2.0 $56.42 0.0 $73.94 8.0 $39.10 46.0 $51.95 7.0 $31.56 7.0 $30.37 0.0 $28.08 13.0 $29.90 Total Direct Salary Costs: 2. Labor and General & Administrative Overhead Total Costs $ $0.00 $1,345.34 $112.84 $0.00 $312.83 $2,389.61 $220.95 $212.58 $0.00 $4,982.85 Percentage of Direct Salary Costs* 184.12% $9,174.42 3. Fixed Fee: 15% of Item 1 & 2 $2,123.59 4. Direct Nonsalary Expenses Travel $505.00 Meals & Motel $0.00 Copies & Prints $0.00 Supplies, Phone, Misc. $120.00 5. Subtotal of Items 1 - 4 6. Subcontract costs 7. Not -to -Exceed Total (Items 5 & 6) Total Expenses: $625.00 $16,905.86 $0.00 $16,905.86 Rounded: $16,900.00 * For Item 2, the consultant should submit a statement of auditable overhead expenses, certified by the consultant's auditor, the sponsor's auditor, the state's auditor, or a Federal government auditor.